Assessment #1

  • As of 04.18.24 | Meter Upgrade | $17,000 per unit | PASSED | Assessment Schedule to Follow

Assessment Schedule #1

  • $17,000 | Pending Board Decision

    • July 1st 2024: $7,000

    • January 1st 2025: $5,000

    • April 1st 2025: $5,000

Assessment #2

  • As of 04.18.24 | Hardscape and Landscape | $5,000 per unit | Failed

Assessment Schedule #2

  • $5,000 | Vote Failed

    • July 1st 2025: $5,000


Recent Ballot Initiatives

  1. Approval for Board of Directors to take out $500k Line of Credit : PASSED

  2. Approval for Meter Upgrade Project: PASSED

  3. Approval for Landscaping Project: FAILED